The last couple of months have been challenging for all of us. I wanted to reach out to our customers to let them know what we have accomplished in the past year to improve our system in lieu of the presentation at the Annual Meeting.  The annual financial statement is also on this website under the Resources tab.

Some of the improvements we have added or in the process of completing are: 

Removed the old storage tank at the 304 well and replaced it with a larger storage tank

Adding a pressure tank at the Nickel booster station

Pulled the Bebe Well and replaced the motor and added column pipe to lower the pump in the well

Added a standby generator to the 228 booster station

Installed an 8" line along Highway 90A W from County Road 153 to the Creekwood Subdivision

Installing filters at the Oak Forest Well

Installed a 4" line on FM 2091N